Previous Page  26 / 84 Next Page
Information
Show Menu
Previous Page 26 / 84 Next Page
Page Background

North America 2018

24 \

World Cement

needs, then the potential exists to develop CO

2

for

delivery and use in existing industrial gas markets.

The size of the overall cumulative amount of CO

2

captured during the project was small, but was not the

primary focus of the project. The cement industry focus

on CO

2

capture has thus far been towards

full-scale capture, which will require years of further

development, high capital costs, potentially complex

integration with the cement plant operations, and

downstream solutions for where to put or what to do

with the captured CO

2

.

The project demonstrates a retrofit system that

could be applied immediately, with low capital costs

and paired with an existing utilisation strategy. The

retrofit capture can be operated and scaled up to match

the downstream utilisation needs.

The next target will be to demonstrate longer-term

capture. A study of ongoing operations will identify

barriers to expanded implementation and scale up. The

gas distribution aspect will be considered by creating an

ongoing supply of CO

2

for utilisation.

Future development will see the continued

expansion of CO

2

utilisation options within the

cement and concrete industry, including growth of the

CarbonCure producer network. New CO

2

utilisation

technologies that grow the demand for CO

2

will

be developed and paired with cement industry CO

2

sources.

If the CarbonCure approaches were adopted

globally, an estimated 82 million t of CO

2

could be

utilised per year to achieve a mineralised and avoided

impact of almost 500 million t CO

2

. This has the

potential to exceed the 442 million tpy reduction

attributed by the CSI to the carbon capture and storage

segment. Further CO

2

utilisation approaches for cement

and concrete production could serve to increase the

total CO

2

demand and impact.

8,9

Summary

This project is an important milestone in

demonstrating the viability of a complete supply

chain solution for the cement industry to consume

its CO

2

emissions and improve the commercial and

sustainability competitiveness of its products. The

consortium felt this project was vitally important,

since it demonstrates a low-cost solution that profits

each member of the value chain from cement to

construction. Having a complete and scalable CO

2

solution is essential for the industry to meet its CSI

low-carbon technology roadmap targets, while raising

profits, lowering carbon, and reducing risks.

Rather than relying on yet-to-be-developed fully

integrated full-scale capture and sequestration of CO

2

from cement plants, the project demonstrates that a

utilisation-scaled capture solution is capitally efficient

and immediately scalable. The time value of carbon

is important as emissions are cumulative and there

is a limited amount of time to achieve the required

reductions. Carbon reductions achievable immediately

are more valuable than carbon reductions in the

future.

References

1. HILLS, T., LEESON, D., FLORIN, N. and FENNELL, P., 2016.

‘Carbon Capture in the Cement Industry: Technologies,

Progress, and Retrofitting’,

Environmental Science &

Technology

50 (2016), pp. 368 – 377.

2. BJERGE, L.-M. and BREVIK, P., ‘CO

2

Capture in the

Cement Industry, Norcem CO

2

Capture Project (Norway)’,

Energy Procedia

63 (2014), pp. 6455 – 6463.

3. KLINE, J. and KLINE, C., ‘Cement and CO

2

: What is

Happening’,

IEEE Transactions on Industry Applications

,

vol. 51, no. 2 (March – April 2015), pp. 1289 – 1294.

Figure 3. Dewars of liquefied captured CO

2

at the

Glenwood concrete plant.

Figure 4. Concrete production using captured CO

2

at the

Glenwood concrete plant.