capacity of 70 000 t. This addition will allow
for better flexibility of McInnis’ expanding
distribution network while allowing for
maximum utilisation of their growing marine
fleet.
In addition to the supplemental storage, a
second loading alley equipped with self-loading
ability was constructed to minimise waiting time
for its customers base.
The project lasted a little over a year and
was completed in time for the 2020 shipping
season.
Ravena plant, LafargeHolcim
FCT Combustion delivered a Turbu-Jet burner
to the Ravena plant, which was installed at the
plant’s main burner. The Turbu-Jet is capable
of firing 31% oil, 100% coal and 100% natural
gas, to meet the plant’s requirements. A
calciner burner designed to fire 100% natural
gas was also supplied.
Rillito Plant, CalPortland
CalPortland was selected to carry out the
Rillito Plant Stage 1 Cyclone Replacement. The
preheater tower is a key component of modern
pyro processing systems. For it to function
correctly and at maximum efficiency, all the
components in the tower must be working
correctly. In the case of the Rillito #4 cement
kiln preheater tower, the lower three stages of
the four-stage preheater were in good condition
and functioning correctly. The same could not
be said for the top or first stage cyclones and
outlet ducts, which had been in operation for
25 years.
The cyclones were not refractory lined and
had been buckled and distorted, and the steel
was worn thin through the years of operation.
The buckling was due to the thermal expansion
of the unlined steel cyclones exceeding
the design parameters, an issue that was
made worse by the steel being worn thin by
the abrasive wear of the kiln feed over the
operational life.
It was determined that there were several
reasons for the early replacement:
f
Lack of refractory lining.
f
Attachment of cold structural walkway and
platform steel to the perimeter of the hot
cyclones and ducts.
f
Inadequate allowance for expansion when
considering current operating parameters.
The design process started with an evaluation
of the tower structure with the aim of
determining early on what structural constraints
the design team would need to contend with.
The Rillito preheater tower is a reinforced
concrete tower designed in the 1960s to the
codes of the day. Structural design codes
and standards have changed since the tower
was built, therefore a complete and detailed
analysis of the tower was required to determine
the structural limitations for the new stage one
cyclones.
The upgrade to the first stage cyclones
and ducts was a successful project and was
installed within the allocated kiln outage
window. Meeting the installation schedule was
only possible with assistance of the plant, the
contractor and everyone else involved in the
kiln outage activities.
The operating performance of the cyclones
has been in line with the predictions of the
model, with the collection efficiency slightly
higher than design. The higher collection
efficiency has not caused any adverse impacts
to plant operation. The redesigned cyclone inlet
and riser duct have delivered the predicted
reduction in differential pressure. This will
provide the plant with energy savings through
reduced electrical energy consumption on the
kiln ID fan. The plant will see this benefit for
the operational life of the cyclones.
Also at the Rillito plant, Bricking Solutions
supplied the plant with a Mini Econ-O-Ring
single arch bricking machine, designed for
kilns with 1194 – 2489 mm (47 – 98 in.)
brick ID. The Mini Econ-O-Ring (MECOR) is
a single arch bricking machine with a single
adjustable frame system that allows the
MECOR to be adjusted to different diameter
combinations within its range. The MECOR is
designed for burning chambers for paper mills,
tertiary return ducts, satellite cooler tubes,
small vessel, kilns and furnaces.
Sparrows Point, LafargeHolcim
FCT Combustion will modify the existing burner
management system at the Sparrows Point
plant, as well as the natural gas valve train,
to comply with NFPA 86 requirements. The
modifications will also improve the operation of
both burners installed at the slag dryer.
Sumterville plant, Suwannee American Cement
Fives will supply Suwannee American Cement
with one Pillard NOVAFLAM burner for the
rotary kiln for coal and gas firing.
Bricking Solutions’ Universal Safety Cage for
kilns ranging from 4 m to 6 m was supplied to
the Sumterville plant.
The Universal Safety Cage is designed to
withstand a solid impact of 114 kg from a
height of 2438 mm. The cage, being half the
weight of the traditional style, is easily carried
by two plant personnel.
97
World Review 2020
World Cement




